State Important Transmission Projects

Physical Progress (No.)
Month Target Actual
April 2019 31 27
May 2019 30 28
June 2019 30 30
July 2019 30 27
August 2019 30 28
September 2019 27 24
October 2019 21 18
November 2019 12 11
December 2019 12 *14
January 2020 7 8
February 2020 4 4
March 2020 4 2
April 2020 0 0
May 2020 4 2
June 2020 8 6
July 2020 9 8
August 2020 12 10
September 2020 17 12
October 2020 14 11
November 2020 16 10
December 2020 18 10
January 2021 21 15
February 2021 18 10
March 2021 18 10