Sl. No Name of Project Capacity Date of Completion

Substations

1 132 KV S/s Srinagar-II ( Switchyard Portion at 400 KV Srinagar) - 26.04.2016
2 400 KV S/s Srinagar Garhwal (2*315+ 2*160) MVA 25.07.2016

Transmission

1 132 KV Srinagar- Simli Line and LILO at 132 KV S/s Srinagar 64.45 CKm 28.04.2016
2 400 KV Srinagar-Srinagar PH Line 29 CKm 25.07.2016
3 220 KV D/C Twin Zebra line from 400 KV S/s PGCIL, Dehradun to 220 KV S/s PTCUL, Dehradun 12.3 CKm 13.01.2017
4 LILO of 132 KV Dhalipur –Purkul Line at 220 KV S/s Dehradun 5.3 CKm 04.02.2017