Ongoing Projects

Sl. No Name of Project Capacity(MVA/CKm) Target

Substations Lines

1 220 /33 KV S/s Jaffarpur 2*50 MVA December 2018
2 LILO of 220 KV Kashipur –Pantnagar Line at 220 KV S/s Jaffarpur 6CKm. November 2018
3 Increasing capacity at 220/132/33 kV S/s Haldwani 2x40 MVA to 3x40 MVA. December 2018
4 220/33 KV S/s Baram 2*50 MVA March 2019
5 132 KV GIS S/s Bageshwar 6*7 MVA March 2019
6 132 KV S/s Patanjali Padartha 2*40 MVA. March 2019
7 220 KV GIS S/s Rudrapur (Brahmwari) 2*50 MVA. March 2019

Transmission Lines

1 LILO of 220 KV S/C of Roorkee –Nara line at 400 KV S/s Puhana (PGCIL) 182 CKm December 2018
2 220 KV D/C line on twin Zebra conductor from Lakhwar to Dehradun and its LILO at Vyasi 81 CKm March 2019
3 132 KV S/c Ranikhet – Bageshwar line 60 CKm March 2019
4 220 kV D/C (Rudrapur) Brahmwari-Srinagar line 186 CKm March 2019
5 LILO of 132 KV Chilla-Najibabad Line at 132 KV S/s Patanjali Padartha ,Haridwar 15 CKm. March 2019
6 132 KV Pithoragarh(PGCIL)-Lohaghat Line 50 CKm March 2019
7 -220 KV D/C (Brahmwari) Rudrapur-Srinagar line 110 CKm March 2019
8 LILO of 220 KV Kashipur-Pantnagar line at 220 KV S/S Jaffarpur - March 2019
9 132 KV Purkul –Bindal Line 10.73 CKm March 2019
10 LILO of 132 KV Sitarganj-Kichha line at SIDCUL, Sitarganj - March 2019
11 LILO of 220 KV Dhauliganga-Pithoragarh (PGCIL) line at 220 KV S/S Baram - March 2019